Overview
This project extends Connemara Trail east of Akron Ave approximately 1600 feet. Also included is the extension of watermain, stormwater infrastructure and sanitary sewer. Pedestrian facilities will include a sidewalk and trail.
Propose Schedule
- Construction Start – July 2021
- Paving – October 2021
- Final Completion – Spring 2022
Follow Us On